Client: HCA UK Ltd

 

Description: Refurbishment and fit-out works within 2 adjacent listed buildings, including structural, M&E and associated specialist works to create new consulting rooms and dedicated CT-scanning suites.

​

A combination of a delayed listed building and other consents, combined with the requirement for unforeseen structural works put the project under both time and cost pressures from the outset. 

​

Academy project managers and quantity surveyors working closely with the client team and the appointed contractor, to re-sequence and re-phase the works to minimise the programme delays and associated cost pressures.